Local Law 11/ FISP case study

How we took one building from UNSAFE to SAFE, while coming in $400K under budget.

Project file
Type
Co-op
Building
Location
East Harlem,
Manhattan
Building
8 stories
35 units
Duration
150 working
days
Scope
FISP facade + roof
Sq ft of roof replaced
3,360
Enforcement actions
0
Saved vs. original budget
$400K

The board faced an UNSAFE classification, with no capital to fix it.

The board of an 8-story co-op in East Harlem came to Daisy already carrying an UNSAFE classification. Every balcony was under controlled access until conditions were resolved.

Financing was the first wall. No contractor would start without the money to pay for it.

The scope was significant before anyone even opened a wall - roof, coping, balconies, railings, sealant, all four elevations.

EIFS repair, caulking, and paint touch-up locations marked floor by floor; guardrail refurbishment noted at all balconies.

The scope on the table

Parapet coping

Full perimeter

Balcony slab repairs

Floors 2–7

Steel & glass railings

All floors

EIFS & sealant program

All elevations

Site infrastructure

4 permits

Full roof replacement

3,360 sq ft

How we managed this project end to end

01

Contractor bidding & selection

Daisy ran a competitive RFP across its vetted contractor pool, built the scope package with the architect of record, and selected the GC on price, timeline, FISP track record, and insurance.

02

Financing navigation

The building had no reserves to fund a project this size. Daisy solved the capital first, structuring a line of credit sized to the full scope before any contractor was engaged.

03

DOB permitting & compliance

Daisy filed and cleared four separate DOB permits, the FISP repair permit, the supported scaffold, the sidewalk shed, and a material hoist, and carried the ninth-cycle FISP report through to its amended, accepted filing.

04

Schedule & budget management

Daisy tracked every phase against the GC’s work plan and held the line on change orders, keeping the job on schedule even when the scope grew mid-project.

05

Resident & building communication

The building stayed occupied throughout, with every balcony under controlled access. Daisy designated access zones, coordinated neighbor agreements, and kept all 35 units informed throughout.

Financial spotlight

The building didn't have the reserve capital to fund a FISP scope of this size. Daisy structured a line of credit sized to the full project, then managed every draw request against construction milestones, leveled bids, and held the line on change orders even after the scope grew mid-project.

Before
Proposed
$1.7M
Proposed budget
After
Final cost
$1.3M
Final delivered cost
Saved
Impact
$400K
Saved

The roof failed, mid-project.

The facade project was underway, scaffolding up on three elevations, and balcony repairs in progress across six floors, when the roof assembly failed. Water was getting in. There was no room in the existing scope, budget, or schedule to absorb a full roof replacement without derailing everything already in motion.

East + west roof

2,360 sq ft stripped to the structural slab, rebuilt with a 20-year modified bitumen system.

Common terrace

670 sq ft rebuilt with a Kemper/Parapro resin system; pavers reset.

Daisy didn't stop the project to renegotiate. A 100-day roof replacement was layered directly on top of the facade project, tracked against the same schedule, financed against the same credit line, without a stop-work order.

The project took 150 working days

0306090120150
Sidewalk shed
10d
Scaffold, North & West
15d
Scaffold, South
10d
Facade, North & West
90d
Facade, South
60d
Roof replacement (added)
100d
Demobilization
20d

The results: Unsafe to safe

The amended 9th Cycle FISP Report was filed and accepted, officially closing out the violation. The balconies came off controlled access. The board that started this process with no funding and an active violation ended it fully resolved, and under budget.

Main roof

Assembly stripped → New system installed

Parapet coping

Cracked coping stones → New zinc coping cover

Balcony railings

Posts removed → Refurbished & reinstalled

Balcony slab

Topside slab cracking → Repaired and coated

Coping detail

Spalled, horizontal crack → New metal coping installed

Bring Daisy to your building today!

Join the hundreds of board members who have already made the switch
Schedule a call