A project this big deserves a team to match

How we run your building's capital work, from bidding through closeout, on time and on budget.

Field update Jul 14 · 9:20 AM
East section · tear-off
Daisy project manager

Original decking better than expected, insulation should go down fast.

15% complete
Value engineering
Daisy project manager

Can we use tapered polyiso instead of a poured cricket at $3/sq ft less?

Scope pushback
Daisy project manager

Replacing all 11 skylights isn't warranted. 3 of them need it.

Bid leveling · Roof replacement 3 bids
Contractor As bid Leveled
Vanguard Roofing $1,310,000 $1,268,000
Harlow Roofing $1,240,000 $1,160,000
Kestrel Sheet Metal $1,095,000 $1,080,000

A team advocating for your building at every step

We level bids, question line items, and push back on scope and cost. And we make sure the plan itself is the right one.

We solve the capital problem first

Most buildings can't fund a major capital project out of reserves. We structure the financing sized to the full scope before any contractor is hired, and manage the draws against milestones.

$1.3M
Financed for one East Harlem FISP + roof project

We keep the project moving

We're in constant contact with the contractors and engineers, on site when it matters, and in the details throughout.

Project schedule · Roof replacement · 205 E Houston On schedule · week 11 of 12
Timeline Documents
Complete In progress Scheduled
Phase
May 4May 11May 18May 25Jun 1Jun 8Jun 15Jun 22Jun 29Jul 6Jul 13Jul 20
Status
Engineer inspection & report
Done
Bid, level & award
Done
Permits & roof hoisting
Done
Tear-off · main roof
Done
Insulation & new membrane
60%
On site
Skylight curbs & flashing
Jul 20
Today
205 E Houston · roof replacement

Project schedule

Week 9 of 12
May 4May 18Jun 1Jul 26
Today
Engineer inspection & report Done
Bid, level & award Done
Permits & roof hoisting Done
Tear-off · main roof Done
Insulation & new membrane On site
Skylight curbs & flashing Jul 20

You get the whole story

Your board gets updates with progress photos, any blockers, plus our recommendations at every step.

Roof project updates · 205 E Houston

Roof replacement

Full tear-off · 12 weeks · May 4 – Jul 26

Submittals
Mobilization
Tear-off
4New membraneIn progress
5Demobilization
#6 July 13, 2026 On schedule

New membrane is going down on the main roof.

  • Membrane torched down — east half
  • Parapet flashing — north edge sealed
  • Skylight curbs — due Jul 20
Crew working on the open roof deck near the skylight
East roof · membrane prep at skylight
New membrane and flashing along the parapet edge
Membrane torching · south skylight
Daisy project manager Sela
Our recommendation

Approve the $7,200 change order to replace the two skylight curbs now. The curbs are due for replacement Jul 20 and doing it while the roof is open avoids a separate mobilization.

Approved roof plan — TPO replacement, 205 E Houston
Approved drawings

Roof plan · A-201

Filed by Vertex Engineering
co-op management company

Ready to stop managing your own projects?